Continuous operation at the reported follow-up
Federal field evaluation · 2015Catalyst-Based Nonchemical Water Treatment System
- Application
- Electric domestic water heater, Frank E. Moss US Courthouse, Salt Lake City.
- Evaluation
- Before/after element inspections, operating measurements and maintenance records for a third-party catalytic-alloy insert.
What was observed
At the 17-month follow-up, no heating elements had failed and elements were mostly clean, with some remaining calcite. Heater operation improved after installation and thermostat adjustment. Soft sediment still collected in the tank; the report allowed for its removal approximately every two years.
Economics and limits
The report’s replacement-cost scenario gives an estimated $1,060 annual net saving: $1,160 in avoided repairs less a $100 annual allowance for tank cleaning, with payback below two years. GSA’s “immediate payback” comparison uses a different baseline: installing a conventional salt-based system. These are site-specific findings, not ZoneGuard savings forecasts. The cooling-tower analysis was modeled, not a tested installation.
A single-site evaluation of another product; not a controlled ZoneGuard trial or a guaranteed household energy reduction.
Read the GSA evaluation and original report ↗